A client reached out to discuss an approach to handle a fire at a compressor station, affecting two compressor units. After assessing the situation, VRC provided guidance and, along with the client, reached a decision to remove one of the units, refurbish a second unit, rebuild rack piping, rebuild all instrumentation and electrical components.
Industry:
Oil & Gas
Services You Provided
Mechanical Construction & Civil Construction
Completion Date:
Within 3 weeks
Problem They Were Having:
Fire at a compressor station
Solution VRC Provided:
VRC removed one of the units, refurbished a second unit, rebuilt rack piping, and rebuilt all instrumentation and electrical components. VRC was able to handle this in three weeks.
Please Note: The images below are not specific to the case study above but are intended to show the variation of our project capabilities.
![cs03-02 vrc-cs1](https://vrcenterprises.com/wp-content/uploads/2023/12/cs03-02.jpg)
![cs03-01 vrc-cs1](https://vrcenterprises.com/wp-content/uploads/2023/12/cs03-01.jpg)
![casestudy-05](https://vrcenterprises.com/wp-content/uploads/2023/12/casestudy-05.jpg)
![casestudy-02](https://vrcenterprises.com/wp-content/uploads/2023/12/casestudy-02.jpg)
![O&G-info](https://vrcenterprises.com/wp-content/uploads/2023/12/OG-info.png)
Do You Have A Project You Need Done?
Someone our sales team is ready to assist you with your project needs.